3.2 Rank B
a) Display “New parts” on identification tag and implement inspection for first 3 deliveries in case of new parts inspection for parts such as sheet metal processed parts etc. at time of new
production, change of supplier and change from internal to external manufacturing (and vice versa). Parts inspection chief shall enter EDP terminal and carry out specific selection of those new parts inspection targeted parts as based on “New parts inspection targeted supplier list” (Form 2).
b) “New parts” that pass inspection on 3rd delivery shift to Rank C from 4th delivery.
c) For “New parts” that fail inspection on 3rd delivery, enter this in EDP terminal, and from 4th delivery onwards display “Inspect” on identification tag and carry out inspection. In addition, in case of failure (NG) on 4th delivery, request corrective action by supplier.