- LC still wait RFI answer
- If we change spec requirement Philips to local brand (as per Phase2) we can save 1.75MTHB + OHP
- We included under the FAS some provision to reprogram if needed.
- We didn’t included the change of graphic panel to follow new room layout. This will be subject to VO
- We excluded the removal and re-installation of item that will be located on the same location (example, FA bell, manual pull-out…). Work to be done by ID or subject to VO.
- BOQ ask for R22 but we price with R407C
- Cooling capacity of 10 AC for Boy Boarding was different between BOQ and AC schedule. We have amended the BOQ to reflect AC schedule.
- AC air chamber (gympsum) excluded. To be priced by ID contractor.
- Suggest ERV vs std fresh-air/exhaust system (VE to be discussed).
- All pipe works located under the gnd floor slab are excluded. New pipe rooting required in this area will be subject to VO involving civil contractor to brake and redo the slab.
- Suggest heat-pump vs std electrical water heater (VE to be discussed).
- All demolition of existing system (M&E) are excluded in our proposal (by structure or ID contractor).
- We based our prelim cost on 8 months duration. If schedule 6 months only, it reduce our proposal by 780 KTHB.