Dear All
About the area separation plan in the tent house is attached.
Please prepare to start work.
[Schedule]
(13/Aug) Safety Audit by CMTH
(14/Aug 13:30~) Final inspection by CMTH with TOC
(15/Aug~) Start to use, up to inspection
[Purchase]
#General
-Line tape : Yellow, White, Red
-Air Line (Code Reel) [Attached Photo]
-Electric Code
-Shelf
-Spot or Box Air conditioner (Cooler) [Attached Photo]
#Safety
-Fire Extinguisher
-Pad lock (2sets)