This is to ensure that potential problems can be identified and that the ongoing viability of the project can be continuously monitored.
Project control generally consists of financial controls such as budgets and time controls such as milestones, which enable the status of a project to be measured. Frequently, a regime of more subjective controls will also be established, such as internal and quality assurance reviews, supported where necessary by external reviews undertaken by specialist consultancy organisations.