Dear all related members
We are evaluating just now for this cost down.
But we have one problem by this activity.
TRID will buy from TER TM-226-2 and TM-228-2 for their production.
But we will change supplier from CH.W to TTTC.
Then TRID will change also.
But They can’t change supplier suddenly.
Because They are not same as us about production plan.
We will have running change for current part (TM-226 and TM-228).
But they will have SOP for New IMV from Sep. 2015.
We should supply to TRID by CH.W after our sourcing change.
Please set APQP meeting for this problem quickly.