Based on the literature, e.g. (PMI, 2000; Milosevic, 2003; PMI, 2005), the authors compiled a list of 56 PMTT and presented the list to the panel of experts. Using 1-to-5 Likert scale (1 means rarely used and 5 means frequently used), the experts rated (based on their perception) the frequency of the use of each PMTT by project managers in industries. The result was compiled and presented back to the panel for evaluation. Based on the rating of each PMTT, the panel suggested a list of 39 PMTTto be used in the survey. The list includes top 37 PMTT that had the rating higher than 2.75. Even though Monte Carlo Analysis and Earned Value Management had low ratings, with their potential benefit to project management, the panel suggested adding them to the list (see Table 3 below).