As we follow up her end May, she update as below, Mr Thevan , our sales engineer will follow up with her and update to you soon.
It’s expected that recommended vendors can be approved (or rejected) early next month. According to internal schedule, RFQ for Oily water treatment package should be in July, PO in Sep of this year, and arrival at site in June next year.
As we follow up her end May, she update as below, Mr Thevan , our sales engineer will follow up with her and update to you soon.It’s expected that recommended vendors can be approved (or rejected) early next month. According to internal schedule, RFQ for Oily water treatment package should be in July, PO in Sep of this year, and arrival at site in June next year.