All pile load test for spun pile dia. 400 mm and 350 mm were finished on August 19, 2014.
Addition earthwork up to level +3.8 m and +4.3 m MSL was under progress and will be finished on end of August, 2014.
The preparation of piling rig at site as following:
The first rig was working at site continuously from pile load test.
The second rig and accessory crane was already certified and put in service on August 20, 2014.
4. The soil resistivity measurement was done and finished on August 26, 2014.
5. Site access road was in progress and will be finished by end of August 2014.
Site construction meeting and site-note
Power plant construction meeting no.4 & 5 were held on August 7 & 20,2014 respectively.
The site note no. NNEG-SN-S-T-C-0001 about pile installation work delay was issued on August 8,2014. JURONG reply by NNEG-L-T-E-A-0011.
All pile load test for spun pile dia. 400 mm and 350 mm were finished on August 19, 2014.
Addition earthwork up to level +3.8 m and +4.3 m MSL was under progress and will be finished on end of August, 2014.
The preparation of piling rig at site as following:
The first rig was working at site continuously from pile load test.
The second rig and accessory crane was already certified and put in service on August 20, 2014.
4. The soil resistivity measurement was done and finished on August 26, 2014.
5. Site access road was in progress and will be finished by end of August 2014.
Site construction meeting and site-note
Power plant construction meeting no.4 & 5 were held on August 7 & 20,2014 respectively.
The site note no. NNEG-SN-S-T-C-0001 about pile installation work delay was issued on August 8,2014. JURONG reply by NNEG-L-T-E-A-0011.