I)-Scope of Construction Work.
A. Embankment Total……………………………………m3
B. Pedestrian bridge total 60 places
C. CBR FOR Embankment Shall be CBR ≥4%
• Selected Subgrade CBR ≥15%
• CBR FOR Sub base Shall be CBR≥ 30%
• CBR ROR Road Base Course Shall Be CBR≥90%-95%
• Reinforcement Concrete (thickness 200mm)(32MPA)
• Garden Island (middle garden) 1,6-2m
II). Road Furniture.
• Construction Work of Lighting Poles in the central road distance 50m each.
• Road Sign
• Road Marking