EN 54E1 Rail
This item shall be full compensation for supplying the rail materials to be
selected by SRT from alternative manufacturers in accordance with the
Specification. To include compensation for all costs incurred in procurement,
inspection, shipping, hauling to depot, off-loading, storing, and placing
materials on the formation. To include all duties and taxes where applicable.
Measurement : Shall be measured in tone.
Payment : Payments shall be made for material delivered and stored / stacked in a place
and manner approved by the Engineer and / or handed over all surplus
material to SRT.
Partial payments of 90% shall be made as the material is delivered to depot
and accepted by the Engineer.
The remaining 10% of the payment shall be made as the material is installed in
place and accepted by the Engineer and / or surplus material handed over to
SRT.