Except for the material, there will be some subtle changes for the housing design regarding the revised DRL.
It means we don't have the sample currently cause we need to do the tooling modification.
We will off from Feb/13 to Feb/23 due to our CNY holidays, so I attached the estimated schedule as below for your reference.
1. Provide 2D drawing before Feb/11.
2. Provide rapid prototype before Mar/02.
3. Arrange the tooling modification after TFP confirmed the drawing or rapid prototype.
4. The tooling modification will be done around the mid of April.
5. Provide the sample for evaluating around the end of April.
Please let me know if you have any question to the above, thank you.
Also, I'll appreciate that you can advise us if the changes for the housing design is OK with TFP today, so we will arrange the 2D drawing ASAP.
Looking forward to hearing from you soon.