The critical path is shown in red arrows which are A-C-E-H-I path with a critical time of 27.30 minutes. Thus,
through the usage of network diagram the activities in the setup process can be balanced and arranged according to
its predecessors. Initially the completion time of setup process is 93.49 minutes as the activities are done
independently. However, through external setup conversion and excessive motion waste elimination the net time
required to complete the setup process improved to a total of 40.932 minutes.