Disposal of the remaining wastes that are unable to be reused or recycled in the approved landfill site.
Preferably, inert wastes such as broken tiles, bricks, plastics should be used for filling the site in areas planned to be vacant space.
No burning of wastes will be allowed.
Non-construction wastes will need to be disposed off in a sanitary land fill to be located within the refinery site in designated green areas.
Decomposable wastes such as food wastes and vegetation may be disposed of by composting.
Hazardous wastes will be handled by a licensed hazardous waste contractor. If this service is not available, the Contractor will need to find appropriate arrangements for incineration, safe permanent storage, or other appropriate methods of disposal.