Dear K Somchai,
I think there is something wrong in the calculation formulas. For example (from building A):
Section B.5 should show complete, but the sum at the bottom is 98.50%. It should show 100%.
Section A.5 same.
Also, some of the completion percentages are not correct, for example building A section A.3 the Concrete GR Ramps should show 100% complete.
When a building has been handed over, it should basically show 100% unless there are work omissions.
Please could you help to check? If you do not agree or if you have any comments or questions please call me so we can clarify together.
Thank you in advance.
Best,
Adam
On Mon, Aug 3, 2015 at 5:16 PM, Somchai Unglertrakul wrote:
Dear Sir,
We are pleased to submit enclosed herewith Monthly Progress Report
No.18 from 1 to 31 July 2015 covering QA/QC Service of Longview
Project 1 for your consideration.
Best regards,
Somchai