We already sent the PO to K.Jakkatorn for overhaul job of screw pump but K.Jakkatorn said that it has lead time around 4 weeks , we can not accept this because in next month our production will ramp up production plan so we needed to use the machine supported big production volume. Our requisition is can you rush and pull everthing to be finish in the end of this month ? It 's big effect to us if job is not complete pls kindly expedite all.