Omission
0414. In case the Supplier fails to supply/ provide any of the items (i.e. machinery, equipments, sensors and armaments etc) within the scope of supply of the contract for construction of Training Ship, the contract price shall be adjusted by deducting the quoted price of the item along with 25% penalty based on the quoted price of the item. If the price of the item is not quoted in the original offer, the Purchaser shall have the right to determine the price of the item based on procurement price of similar item by the Purchaser through DGDP/ NSSD, Dhaka or any other means. However, if the omission/ correction is made under mutual agreement between the Purchaser and Supplier no penalty will be made.