According to the meeting with the "PEA" on 25 sep.
On the issue of the pipe line was obstructed by power pole at kp.27.
on that meeting, we combine the data level (top of pipeline and bottom of footing of power pole)
As informal expected.The power pole was install the top of pipe.
Light pole on the pipes and the electricity is of the opinion that it should be moved to the post and the PTT agreed.
And from the meeting yesterday, the PTT request to move the poles, but not the scope of the TRC report that TRC. This has not made a conclusion.
.