I know we have spoken about a few things that need to be done and I wanted to ask if you could report on status and expected completion of the individual tasks. As I emphasized on Tuesday, TV1 MDR documents is a much higher priority than TV2 (which should wait for remarks from AP and FW at end of March anyways). The other item that was urgent was the TV1 Nitrogen system classification design pressure changes. We are very curious as to the effort on this.
TV1 MDR
• Total consolidation of all MDRs (including all Equipment supplied, instruments, EHT, materials supplied, Deeline work, etc. All construction QA including hydrotest packs and loop folders)
• New CDs (requesting 6, some sent to our Calgary office, some to UK)
• Hard copies (please arrange for a quote quickly so we can understand the cost of these copies (2) in Thailand versus Canada) AP needs hard copies.
• Are there any other items holding up the coordination and consolidation of all of the MDRs?
• We do not want to wait to do TV1 with TV2. This is about to hold up start up for AP.
TV2 MDR
• Current status - will be wanting to wait until we get the comments back, so do not combine with the TV1 effort, please.
Nitrogen System Classification
• Please give us the status of documentation changes and possible NCRs that may be required (like test pressures, isometric information, etc.)
Thank you. These are becoming very important and we need to provide the TV1 work as quickly as possible.