- Now we fabrication Flush Type Cleaning Door shell be finished to day and inspection before weld by QC. PAE on tomorrow (21-08-2014) after that request to PTTEP for inspection again and start weld in the next day (22-08-2014).
- Annular plate , rafter , top angle and stair way are fabrication finish and we sent to PAE Shop for painting in afternoon time today.
- Another part and accessory of tank we order material already and plan for fabrication continue. (Now some drawing is not approved) *Tank sump for drainage must be completed first before tank bottom erection but now drawing not approved.
- About manpower and equipment mobilization we plan on the first week of next month but we will be sent the name list to you in as soon as possible. Manpower and equipment including tools will be mobilization for safety introduction and other preparation before start work at field about lesthan 1 week.