Temporary wall for separate area
Clearing, Grubbing
Excavation
Backfill with excavated material
Disposal
Compoacted Sand 0.10 m
Lean concrete 0.05 m.
Concrete
Reinforcing Steel
Form Work
Steel trowel
Motra adjust slope
Satainless ladder
Checker plate cover W/ handle
Water stop 8 "
Scaffolding for form work
Box out & grout for (in-out) pipe
Excavate for discharge Pipe Dia.315 mm. HDPE PN 6.3
Back fill & Repair Public road