The Buyer is to provide workers, electrician &
necessary tools to assist in the installation of the equipment onto the production
line. A space of 2.0 m length is needed after the IS machines for the installation
of the hood onto the line. The production line is required to stop production of
bottles for 1 hour during which the hood is being installed. All parts will be tested
to be operating normally before the hood is installed onto the production line. On
the commissioning, the bottles coated will be tested for the CTU & uniformity
using the AGR CTU measurement equipment.