The attached are EGAT's approval certificates of factory test report and shipment.
However, the CIF date will be now very much delayed from the schedule (Dec 30, 2015) in the P.O. for more than 50 days.
This will impact a lot to our installation schedule.
Instead of raising the penalty issue due to the delay, may we request you to make an air-freight for just 6 sets of the DS as follows;
1) 1AB10-1, air-freight for 3 sets
2) 1AB10-2, air-freight for 3 sets
Please take an immediate action to lessen the impact.