Dear K. Anuphong,
See my comments below.
• I have no problem on this agreement. You can cover all causes and it looks like our standard agreement.
• Please let the owner of this project review in causes again. (Money amount, days, %,…..)
• Did suppliers agree on this agreements? If suppliers need to revise any causes, please let me know before final sign.
• Please keep me in the loop if there are any changing in this agreement from both sides.
• Please take out my name from examine committee.
• Could you please provide quotation support amount 2,944,000 baht?
Because I did not find any tie number in documents that support CAPEX approval.