8) Options:-
8.1) Car parking
8.2) Wash bay area for tool cleaning with wastewater treatment system under ISO 14001 requirements.
8.3) Hazard waste area Build the buffer zone to prevent the used oil / chemical leak into public under ISO system requirement.
8.3) Drain system outside kitchen for grease traps and waste water treatment plant ISO 14001 system requirement
8.4) Illumination system to meet the regulation requirement and ISO 14001 system.
8.5) Workshop designs interior wall partition with new technology available to movement extends or reduce the space area.
9) Additional provide
9.1) CCTV can monitor by internet and key card system to office area
9.2) Air condition chiller type system built in office for save electric cost more than split type.
9.3) LAN, Telephone, Water utilities, Electric
9.4) Pressure test area size 2 m x 3m x 1 m available to do the pressure test tool.
9.5) Intend to build for a role company model of industrial park
9.6) Confirm will finish building in 9 months. Worst case if not finish in time line back up office and workshop spare available for us.