Once the information necessary for the generation of a time-line chart has been input, the majority of
software project scheduling tools produce project-tables-a tabular listing of all project tasks, their planned
and actual start and end dates, and a variety of related information(Figure 27.4). Used in conjunction with the
time-line chart, project tables enable you to track progress.