As notice in the site meeting that our 3000kVA Transformer urgently required the services and maintenance (re insulations) on the secondary side feeder cable.
Now the material/equipment required for this task are available on site. The services work will started on Wednesday 15th June 2016. From 08.15 am. To 17.00 pm.
Once the work finished and tested, power supply will be back on ASAP. Please also find our working plan, risk assessment etc. attached for this task.
I do apologized for any un conveniences to you and your workforces. Please make sure that you planned to work without electrical power supply for this period of time.