1) Start and completion dates for engineering, procurement, contract,
construction, pre-commissioning and commissioning.
2) Material delivery and shipping periods.
3) Site mobilization and construction activites by subcontracts.
4) Mechanical Completion, Ready for Commissioning, Completion of
Commissioning and hand over dates.
5) Major milestones completion dates.
Progress curves are developed to monitor Home Office and Construction progress from Level 2 CPM networks. The curves are updated weekly & monthly to display actual progress versus planned progress and will be issued as a part of the Weekly & Monthly Progress Report. It is based on the approved Project Master Schedule and covers: