Dear Dr.
I will send as request within next week as belows,
1. Revise drawing as following comments.
Within 22/3/14
2. All cost breakdown for Electrical and etc…system with back up QT from supplier.
Within 28/3/14
3. Work schedule for Electrical and etc…system base on Civil work schedule.
Within 22/3/14
4. All materials document and product specification submit by subcontractor for approval (RFA)
Every Saturday.