The total project cost is sensitive to the interest rate applicable during the construction period. If the interest rate is higher than expected, project cost increases accordingly. The higher project cost requires a larger amount of permanent financing. As discussed in Chapter 3, the sponsors of a project can eliminate their interest rate risk exposure by arranging interest rate swaps. The bank would receive a fee for arranging the swap transaction, which would have to be added to the project cost.