According I contact to Kyoritsu maker about " schedule inspection machine Pre-Heat and Withstanding "
They confirm :
1. Pre-Heat MC & Withstanding Auto MC : Maker confirm MCP can go to Inspection on 15 Feb'16
2. Repair & Improvement comment : 16-18 Feb'16
3. Send to MCP : 19 Feb'16
4. MCP Install New MC : 21-22 Feb'16
5. Start Trial for send to QA : 23 Feb'16
6. Measurement : 24-26 Feb'16
7. Start Mass Prod : 1 Mar'16
Place : Prachinburi province , 304 Industrial.