Dear K.Simon Lee
With referance to K.Jang e-mail below,we had disappoint very much for your coordination with your venders.
You had committed to requested your vender to supervised in start up and test run of GEG & Power Management
SGC including CNG Loading Facility whenever we are ready to do before we had agree on Taking Over Certificate.
Now you can not coordinate with your venders as our requested.For the equipment test run schedule of GEG & SCG
we had inform you since early of February but we did not received any respond from SCT.Before we had set the
schedule we had coordinate with CAT by sending the sales gas composition from our operation and gas flow rate which
CAT had consider the gas composition and gas flow rate he said it is possible to run GEG.After K.Jang had meeting with
CAT without UAC joint the meeting,he proposed to postpone the test run schedule of GEG & Synchronise test to do on
the same time of The test run schedule of SCG on 17-21 March 2014 by refering to the fluctuation of PEA Power .We can not accept the schdule due to
1) the volume of sales gas may not enough for running of GEG and SCG on the same time.We had inform you earlier that
we would like to test run GEG to check the fuel consumption of GEG after the test run finished we will stop GEG and start
to test run of SCG .
2) For the fluctuation of PEA Power,we have install under voltage protection to protected our equipment to be not damage
in case of PEA Power fluctuated besides PEA has taken out some load from power line supplied to UAC plant and take more attention at Phomphiram Sub Station to steady power supplied to UAC Plant.Then PEA Power will be not make serious
problem to our operation .
In this regards we will confirm our schedule for test run of GEG to be started from 10 March 2014 if not its rather difficult to do after the test run of SCG since we have plan to supplied CNG to PTT our customer continuously.Then it will effect to invoice payment which UAC will pay all of remaining payments after finished of all equipments test run.
For SGC and CNG Loading Test Schedule be accepted but we would like to know more detail of the test schdule due to there are many parties concern especiially for the calibration of CNG Meter. We much inform government official for doing this and
PTT for withness of CNG Meter Calibration including providing of CNG Truck .
However,please be noted that the GEG test run schedule can be not postpone and the vender cost for any test shall be responded by SCT in accordant to contract.
Your due understanding and good cooperation would be appreciated.
Best Regards
Charoonrith Khampanya