Dear all concerned ,
I’d like to send you Rev.1 - Master schedule of May & June & Forecast Jul - Sep
Cause from
1.Foton Trial period ( 1153 & 1113 ) cannot run as plan , have to switching
2. Foton Trial period ( 5257 ) cannot run as plan , postpone to July
3.Fuso FV51JKD3RDH3 #19 , postpone to end of July , cause from issue of MMO
4.Fuso FN62FM1RDH1 # 501 , separate production to be 3 units and then 9 units , cause from trial new engine parts & Frame
Please see detail as att. file.
Remark : QAD will input next week , cause from the system not working now