5.3
Commissioning
Due to the level of pre-assembly and testing at the site of manufacture, on-site commissioning
requirements are minimal. Following an internal inspection, the control sleeve should be stroked
manually to ensure post-transport alignment.
Electrical connection is required to the Electro/Hydraulic actuators and a junction box is provided
at the skid edge for control and instrumentation hook-up. The Hydraulic system then requires
priming.
Operational and insurance spares together with extended support are offered as CiBAS
Support Package options.