For the first question, I’d like to know how the system perform If there are request for partial surrender or adding top up on the monthiversary due date? If the monthly charge was done before partial surrender, the remaining unit will be decreased or not? I think the UAT will answer my question clearly.
The second question is a normal practice of unit link product for all company. My question is why U&I team did not join the FSD walkthrough with CSC yesterday?