There are some unanswered questions about the
relative economies of scale necessary to make the
proposed relationships work. For example, is there
currently enough treated ef¯uent produced by the
waste water treatment plant to fully support the system?
This master plan was designed for a 25-year
projection showing expansion of the waste water
treatment plant. This depends on a larger Choctaw
population. The more water treated, means more water
to support the system. The current 416 000 gallons of
effluent produced per day might be sufficient to support
a scaled down version of this plan. There would
also have to be research on the quality of water needed
for each system, and what engineering methods would
be required to achieve that quality.