Dear P’ Kovit and all concern.
The solution in this point for K-Ken1 ;
CKT in-charge already explanation the current situation to Buyer Isuzu, Then they’re will set meeting with team to consideration acceptable within today (16th Oct) , And answering reply as soon.
If this case not clear they’re will invite CKT and S-Cal to more explanation on next week.
Such as no time for implement within this phase, To continue use of part this condition acceptable by Isuzu !!! It is no choice.
For my opinion in next time countermeasure,
- By strongly progress following up improvement items to Off tool Off process implement “ Next phase K-Ken2 end of Nov. “
IRC an action : Make plan repair mold marking size from 3 mm. 5 mm.
: Make plan mold polishing (Waiting confirmed by Isuzu)
The background of this problem is ;
For more detail , The also IRC supplier already completed mold making and to mistake position of material mold marking “ EPDM “ Due to this root cause, Not clear more discussion drawing detail before start work between CKT R&D , Pur. Dept. with IRC supplier. Might be S-Cal in-charge not join kick off activities ???
In my opinion In nearly the future if have any VAVE , New model or other activities if have any more ;
S-Cal Our team especially PE (include R&D job work) and QA need to joint meeting and co-check activities at supplier site together work with CKT R&D. To prevent weak point and keep on target time in this matter.