The manufacturer shall hand over a copy of the authorisation and documentation of all test
reports for both newly developed and for trains already in service. During the development of a
train the manufacturer shall submit all documents driving the technical design and operational
calculations latest within 3 months after NTP. The manufacturer shall clearly define which
documents and certificates he will provide during the design period for approval by the Client.
The manufacturer shall submit a submittal plan latest 3 months after NTP. All documents must
be handed over at the latest prior to acceptance by SRTET.