Dear team,
It is clear that status of project timing shows a delay of at least 3 weeks.
However, what makes me more uncomfortable is that there is very little “visibility” of what work is absolutely necessary, day-to-day, to ensure no further delay to timing.
The Bosch C/RE team have made several requests to include overlapping installation work for the steel structure > roof panels > walls and louvers. However, when we check on progress this does not seem to transfer over to actual work by TNP.