The ongoing projects include: the KhlongYai Multipurpose Jetty in Trat Province worth Baht 739 million which is 47% complete, the Rock
Top Up for Klong-Dan Erosion Protection Project worth Baht 272 million which is 83% complete, the Construction of Flood Prevention System,
Pa Sang - Ban Paen Phase 1 worth Baht 182 million which is 84% complete, the prevention project for Mae Chan District in Chiang Rai Province
worth Baht 140 million which is 55% complete, the prevention project for Muang District in Chiang Mai Province worth Baht 233 million which
is 3% complete, the Thai Tank Terminal, New Berth 2B, Map Ta Phut, Rayong worth Baht 208 million which 75% complete, the Expansion of
LPG Facilities of PTT worth Baht 1,490 million which is 13% complete and the latest project is the Construction of Concrete Retaining Wall at
Klong Sakaengam worth Baht 400 million.