Could you please let me know that is it possible to improve the a/f app. week 46 for “Thrust Collar” or import them via air freight? Because the 2 pending orders for “Organo” is amount 5.7 million baht and these orders was inquiry before so that it should not be delay! The T200 quantities for these orders are 290pcs with gearboxes I thought that the assembly lead time will be 1 – 2 weeks so that these orders will be completed app. week 48 that mean we will delay for a month and customer cannot accept this. If we cannot improve lead time, it is so difficult to get new project or order from this customer because they will lose a confident with us . Please consider and let me know me your feedback. Thank you for your help in advance.