A number of agencies were responsible for project
implementation, reflecting the complexity of the water pollution control sector and the different
responsibilities and mandate of each agency. Components 1-3 were led by DENR’s
Environmental Management Bureau (EMB). Component 4 was implemented by the Laguna Lake
Development Authority (LLDA). Components 5 and 6, and also part d of Component 1, were
carried out by Metropolitan Waterworks and Sewerage System (MWSS). Coordination of these
agencies and day-to-day management of the project was carried out by the Project Management
Office (PMO) within DENR. General administration (including procurement, financial
management, selection and contract management of consulting services), and progress reporting,
was provided by the Foreign Assisted and Special Projects Office (FASPO), also within DENR.
The Pasig River Rehabilitation Commission (PRRC) and the Manila Bay Coordinating Office
(MBCO) were involved in the activities to harmonize water quality monitoring