Dear. P’ Paitoon
Please inform to SCT for Load test equipment recommendation from UAC. We checked equipment test result as follows,
1. Sale Gas Compressor ( SGC )
Remaining work
1.1 Submit the final alignment main motor report of SGC to UAC
1.2 SGC testing not complete. (Defect cause from High temp. 2nd state). SCT should be coordinate to GET to modify concept and send the SGC report to UAC
1.3 Addition support not complete. ( Vibration cause of Sale gas pipe line ) SCT should be modify the correct pipe support.
1.4 Ball valve leakage at hand wheel 2 Set
1.5 Submit operation design of PV1 E6007 ( Please see below the picture )
2. Load Test ( CNG Load-Out )
Remaining work
2.1 ESDX-6003A The function is incorrect.
Concept from UAC for operation this cause.
- Alarm Light 1 ( Green ) will be to working when finish loading or stop filling panel
- Alarm Light 2 ( Red ) will be to working when start loading or start filling panel
- Alarm Buzzer will be to working when ESD push bottom
2.2 Please submit the CNG operation manual to UAC
3. Gas Engine Generator (GEG)
Remaining work
2.1 Please submit the GEG Load Test Report to UAC
2.2 SCT and GEG should be change cooling water the correct with mixing CAT coolant ( Drinking water or Demin water )
2.3 GEG running test not complete. ( There are also many problems waiting CATERPILLER checked again, After the change of new cooler water system.