At last time with schedule from K.Thanawut and conclusion with K.Phark yesterday the "Install seal air fan" task will combine with "Install counter weight" which working day will be reduce 2 days per each unit work. So, the planning should be as below.
1st unit shutdown duration 15 -23 Oct 2015 2nd unit shutdown duration 23 - 31 Oct 2015 3rd unit shutdown duration 31 Oct - 5 Nov 2015
Please find last plan submitted by K.Thanawut for you reference and please submit us plan according above detail.
Thank you & Brgs krub.
S.Natthapon