For avoidance of doubt, in case the delay is caused by works ofEGAT and PEA that are not
within boundary of the Facility Site or relate to fiber optic cables and the air brake switch to
be installed within such boundary, the Consortium will not be liable for the Delay Liquidated
Damages.