Dear P’Keaw
May I information for New Year Maintenance Shut Down 2015/2016 krab.
I have plan to PM AHU-2 as below scope.
- Clean cooling coil
- Replace V-Belt and adjust alignment
- Inspection & cleaning EC motor.
- **Inspection internal sealing inside Machine(Special requirement)
So, after we finish PM work. I will confirm Dust data for information later.
Best Regards.