Fig. 9 shows the number of cases where the system enters
the cascading phase due to inefficient operators’ reaction to the
initial electrical failure (S4). Approximately 85% (12 243) of
the 14 468 critical overloads lead to cascading electrical outages.
In these cases, operators don’t apply the appropriate actions
quickly enough due to missing, imperfect or partial SA.