I have just visited the unit 10 minutes ago. I am very upset that there is extremely limited progress on site since my last visit several days ago. That day that I met you two, there was no construction staff working on site at all. But I was very polite not to bring it up. I listened and believed that SorSua is doing your best to complete everything on Friday Jan 10. K.Oui specifically said that everything including equipment installation will be completed on Friday, before the Bkk shutdown next Monday. Ome and myself believe you since you said it in front of us personally. Ome then plan an important dinner party on Jan 15th.
So when I went in the unit today and saw that almost nothing is changed (except ceiling is plastered), I was very upset and confused. I recommended SorSua to Ome. That was why he chose your team for his important project. I am very upset that, because of me and my recommendation, he could not settle in after his son's birth for half a year.
So I strongly suggest that SorSua try everything to finish everything on Jan 15th as promised. No matter Bangkok is shut down or not, I don't care. Please finish it. I cannot make excuses for your team any longer.