It has become somewhat obvious that our “site memos” issued to the respective trade contractors responsible for such issues are being disregarded and/or ignored, albeit the very same site memorandums are also CC’d and issued to the project management team, as such we now respectfully request that (PPS) as the project manager’s expedites and coordinates the removal and/or relocation of the water tank at this location accordingly in order to mitigate the delays.