Q44. In a system development project, a flowchart of the development process is created to
perform quality management. Which of the following is an appropriate purpose of
using such a flowchart?
a) To consider where and what kind of problem is likely to occur in the work processes
b) To determine whether the usage rate of the system is within the expected range
c) To identify the relationships between major problems in project execution and latent
causes of the problems
d) To assess the frequency of problem occurrence on a per-cause basis in order to
resolve the causes of the most problems