3.2 VIPER MLV IA FLIGHT-LINE SET UP
The following is a detailed discussion of equipment set-up (Figure 3-2, All Sheets) while performing aircraft maintenance using the Viper MLV IA system. This section contains power connection, Viper MLV IA self-test connection, interface self-test connection, and a typical avionics connection.
Prepare the aircraft for maintenance per the appropriate Technical Order.
On the AVIONICS POWER panel and SNSR POWER panel, set all power switches to the OFF position.
On the HEAD-UP DISPLAY, verify that the SYM and BRT controls are rotated downward to the OFF (Detent) position.
Apply external electrical power and cooling air per appropriate T.O.